Telecity Data Centre

PHASES 2 & 3

Project Details:

Location: Skondal – Stockholm, Sweden
Client: Telecity Group AB
Project Managers: Telecity Group
Consultant: DataProjeX (Turn-Key M&E) + MEIT Phase 3
Duration: 9 months | Aug 09 to April 10 Phase 2 | July 11 to October 11 Phase 3
Value: EUR €26 Million (Phase 2 €20 Million | Phase 3 €6 Million)

Scope:

  • Turn-key. Complete DC project including some construction works & the entire fit-out.

  • Design, procurement, installation, testing, balancing & commissioning of HVAC / Mechanical & all Electrical systems for approximately 2500 m² Data Centre.

  • 9 MW facility, including Generators, UPS’s, PDU’s

  • 4 x 1.3 MW Chillers + associated CHW CRAC units